October 14 Medical Office Building Updates

10/14/2021
๐‚๐š๐Ÿ๐ž๐ญ๐ž๐ซ๐ข๐š
- Cafeteria renovations are in full swing! Work has begun on the underground piping.
- The new freezer and cooler is scheduled to be delivered in November. Over the next two weeks, wall framing will continue as well as installation of the windows.

๐Œ๐ž๐๐ข๐œ๐š๐ฅ ๐Ž๐Ÿ๐Ÿ๐ข๐œ๐ž ๐๐ฎ๐ข๐ฅ๐๐ข๐ง๐ 
- Rough ins, drywall, glass and glazing work continues.
- Ceiling work should start next week in Tact 1.
- Drywall will be hung in Tact 5.
- The rooftop units were delivered today.
- The generator and transformer should be installed late next week, weather permitting.

๐Ž๐ซ๐ญ๐ก๐จ๐ฉ๐š๐ž๐๐ข๐œ
- Drywall taping continues.
- 75% of the building is primed and the first coat of paint is complete.
- Lights are being installed.
- EIFS started last week and should be completed next week. Windows will also be installed by the end of next week. All work is weather dependent.
- Plant Operations will be moving furniture out of the breakroom this week, and construction will begin on Monday, October 18.
- Work continues on the physician parking lot and old MRI parking lot area.
- Asphalt should be completed by the end of the month.
- Case work is in the process of being installed in Radiology.
- Flooring installation started this week.
- The new equipment is scheduled to be delivered early November.
We hope you have a chance to swing by and see the exciting progress! Thank you for your continued patience.
 