October 21 Medical Office Building Updates

10/21/2021
Work will begin under the canopy next Tuesday in front of the hospital.

The cafeteria is still in the demo phase, and the flooring is being removed. The cooler and freezer is scheduled to be delivered November 8th.

The parking lots should be completed by the end of next week.

Glass should be completely installed next week in the new Medical Office Building. In the next two weeks, the canopy will be brought in to be set.

The curb for the new parking lot is being poured at the orthopaedic building. The EIFS work is complete.

Work in radiology will be complete next week. The main lobby renovation will start in the middle of November.
 