August 5 Medical Office Building Updates

8/5/2021
At the Orthopaedic addition, the carpenters are framing interior walls. They're also performing additional framing at all openings, windows and doors to accommodate the exterior finish. Electricians are beginning conduit piping to the new addition.

Superior Concrete poured concrete on the second floor of the new medical office building. The plumbers are installing overhead piping in the western portion of the first floor.

Carpenters are installing plywood wall sheathing and detailing the gypsum board sheathing at the main entrance canopy.
 