August 12 Medical Office Building Updates

8/12/2021
Concrete has been poured on the second floor of the medical office building. In the next two weeks, the perimeter wall framing and sheathing will begin. Roofing is anticipated to begin at the end of August.

Bricklayers are busy designing the front entrance of the hospital. Be sure to swing by and see the finished product soon!

Roofing is beginning soon at the Orthopaedic addition. This will allow interior work to commence.

Drain work is still in progress around the interior of the hospital. Please be patient, follow our signage and do not hesitate to ask for directions.
 