August 26 Medical Office Building Updates

8/26/2021
The stone layers have completed 40% of the thin stone wainscot at the orthopaedic addition. HVAC installers are running main above-ceiling duct, and the drywaller is in the process of hanging above-ceiling sheetrock. Interior electrical and plumbing rough-ins are 90% complete.

The main parking lot in front of the hospital has been demolished. Approximately 60% of it has been stripped of asphalt and concrete.

At the medical office building, framers, plumbers and electricians have been very busy on both the first and second story construction.

Drain work is still being completed inside the hospital.
 