August 26 Medical Office Building Updates

8/26/2021
The stone layers have completed 40% of the thin stone wainscot at the orthopaedic addition. HVAC installers are running main above-ceiling duct, and the drywaller is in the process of hanging above-ceiling sheetrock. Interior electrical and plumbing rough-ins are 90% complete.

The main parking lot in front of the hospital has been demolished. Approximately 60% of it has been stripped of asphalt and concrete.

At the medical office building, framers, plumbers and electricians have been very busy on both the first and second story construction.

Drain work is still being completed inside the hospital.
 
Sort by: Name Date Size
237037840_47021...
Size: 569 kB
Uploaded: 9/15/2021
237856889_47021...
Size: 363 kB
Uploaded: 9/15/2021
239010921_47021...
Size: 462 kB
Uploaded: 9/15/2021
239540035_47021...
Size: 504 kB
Uploaded: 9/15/2021
239929685_47021...
Size: 588 kB
Uploaded: 9/15/2021
Wabash General Hospital logo
Back to top